Timeline:
2021,22,23,24,25 - serious boiler issues and repairs needed in excess of $15,000 per year
2022 - Water Main Break - cleaning and replacement of air handlers, coils etc.. for ventilation purposes were cleaned and replaced for an antiquated and old system.
December 2023 - Steam leak discovered and insurance claim started for lower elementary and activity room fo abatement and flooring replacement during summer of 2024.
April 2024 - Study of the building completed and presentation to the board
April 2024 - EMS insurance denied coverage to the entire building because of lack of updated mechanical systems, boilers, potential roofs, and electrical. District tried to get other insurance. This was also denied.
May 2024 - Conditional approval from EMS insurance with district assurance of completing projects within specified timeline.
May 2024 - Bid notice sent and bids received for summer asbestos abatement projects in lower elementary and 5 HS school classrooms.
June 2024 - Site Logic finalized project at 12.3 million dollars with additional funded for municipal advisor, attorney fees.
July 2024 - asbestos removal in lower elementary and HS rooms
August - floor replacement in lower elementary rooms, non- wax floors - HS rooms will be completed when all rooms are done - all floors will be sanded and polished per the project to save yearly dollars on waxing for the district.
September/October 2024 - Bond Sale approved by TPS Board of Education
October 2024 - Bond Sale
October - May 2024-2025 - Project Narratives submitted, architectural designs in mechanical, electrical, plumbing, controls, and general contractor were created.
March - April 2025 - Bid notice approved and sent to Truman Tribune
April 14th, 2025 - pre-bid walkthrough
May 8, 2025 - Bids opened
May 2025 - 2nd Conditional renewal by EMC insurance based on project completion. Plans submitted.
June 5th - Bids accepted by the board in mechanical, electrical, controls and general contractor service
June 16th - Bids accepted for asbestos removal in July 2025
July 2025 - Asbestos abatement of HS rooms and gym addition, band, choir, ag classroom and library scheduled, permits issued by Mn. Dept. of Labor - Inspector assigned.
July / August - Planning meetings for summer 2026 work